Project/Contract Title: |
SMC# 1210 / Modifications to the Parkway Gate GSFC
Contract# 663000 30597 |
|
POC: |
Chet Neubauer - Parson's Infrastructure (301) 286-6921 |
|
Project Location: |
Goddard Space Flight Center, Greenbelt, Md. |
|
Contract Value: |
$176,259.00 |
|
Current Schedule: |
Completed |
|
Completion Date: |
May, 2007 |
|
Project Engineer: |
John Jones |
|
Project Description: |
SMC was contracted to install a new guard-house with new foundation. Project also involved installation of new highway signage, re-stripping of all lanes, entering and leaving the guard-house (in and out of the access roads), and installation of new street lighting for the guard house. |
|
NAICS Codes: |
236220 Commercial & Institutional Building Constructions. |
| |
|
|
|