Project/Contract Title: |
SMC# 1217 Masonville Marine Terminal - Storm Drain Relocation, Phase 1 & New Connections to 48-Inch Water Main. |
|
POC: |
Tucker Waite - Joseph B. Fay Company (410) 355-2220 |
|
Project Location: |
Masonville Marine Terminal - Childs Street - Baltimore, Md. |
|
Contract Value: |
$853,603.89 |
|
Current Schedule: |
Project started Oct 22, 2007 |
|
Completion Date: |
Approximately 8 months |
|
Project Engineer: |
Chuck Cross |
|
Project Description: |
Excavation and installation of 945 lf of 48" steel coated water main, (2) 48" Butterfly Valves, (3) Manholes, and (1) Combination Air Release / Valve Vault. Installation consists of 50 ft lengths of steel pipe at approximately 20,000 lbs each, requiring 2 excavators and special ordered high-arch spreaders for trench boxes. |
|
NAICS Codes: |
237110 Water and Sewer Line and Related Structures Construction |
| |
|
|
|